What is our process?
If you have made the decision to work with
us, be prepared to provide us with the lot number, parcel,
address, city/county, associated building department and
permit number [if available]. Reminder: on new construction
projects it is helpful to have directions to your jobsite
and multiple contact phone numbers.
-
After your print is
reviewed, we will schedule a time to rail and pour
footings. At this point we will need the building permit
number to call for an inspection prior to pouring the
footings. It is helpful to have the excavating
contractors number for reference. Note: adequate site
access is required to get our equipment as close as
possible to the project work area.
-
Once the footings have
been poured and are substantially cured, the footing form
rails will be removed. Then we will schedule a second trip to
your site to form the walls with our aluminum forming
system [this is usually scheduled to occur within 1 -
3 days]. Our computer system assists us by generating an
inventory of items needed to form your project.
Click picture below to view a sample document
-
The placement of the
aluminum forming systems is a labor intensive task and
pending the placement of rebar, window buck, egress
window frames, beam pockets, door opening, or other
items it can take one or two work days to complete
before ordering and pouring concrete.
-
We will schedule another
trip to the site to remove/strip the form system. Once
the form system is removed exterior drain tile and
peastone must be place round the exterior of the
footing. Dampproofing or waterproofing must applied to
the below grade area of the foundation and inspected
prior to backfill.
Click
picture for enlarged view.
|